Regen has responded to Ofgem’s consultation on transforming the connections experience, calling for greater transparency, stronger accountability and faster action to address problems faced by developers.

Regen has responded to Ofgem’s consultation on transforming the connections experience, calling for greater transparency, stronger accountability and faster action to address problems faced by developers.
Ofgem’s end-to-end review is a welcome opportunity to address the significant challenges facing network customers, from delays and rising costs to errors in grid connection offers. Tackling all these issues is needed to make connections faster and more predictable, bring clean energy generation and storage online and give businesses more certainty. The reforms suggested in this consultation can help rebuild developer and investor confidence if they give customers a clearer basis for planning their projects, and hold NESO and network companies to their delivery commitments.
How quickly those protections take also effect matters. Ofgem can act now by improving its guidance for determinations while it develops the full package of reforms. Regen is calling for an accelerated timetable so the new protections can take effect as soon as practicable and cover existing connection agreements.
Transparency must sit at the heart of the new framework. Customers need to understand how their connection dates and costs have been set, including the Construction Planning Assumptions (CPAs) and reinforcement works that underpin them.
Connection offers should include itemised costs and be accurate before they are issued. Customers should never be expected to accept an offer containing known errors on the promise that these will be fixed later.
Ofgem should also require consistent public reporting on network performance, including offer accuracy, query resolution and delays. This would help identify systemic problems and hold all parties, including NESO, to account.
Developers currently carry significant risks when connections are delayed or costs increase. As such, NESO and network companies should be accountable for issuing offers with realistic connection dates and accurate cost estimates. That accountability must extend to delivering connections by the agreed dates and at the agreed costs, with any changes clearly explained and justified.
Regen supports stronger protections through:
Networks should also have stronger incentives to offer earlier routes to connection, including non-firm, technical limit and phased connections.
Ofgem’s consultation raises the possibility of bringing the new licence obligations into effect at the start of the next electricity distribution price control (ED3) in April 2028.
Customers are already dealing with delays, rising costs and unresolved errors in connection offers. Waiting until April 2028 would leave those customers exposed to further delays and cost increases before stronger protections take effect.
Regen is calling for Ofgem to set out an accelerated implementation timetable, with clear, dated milestones and protections that apply to existing agreements as well as new ones.
For more information on the Regen members Grid Connections Working Group or any queries regarding the consultation response please contact Hannah Stanley.